November Community Update

Construction on the new hospital is advancing steadily, even with the welcome addition of much-needed rain. The project is on track as contractors continue to place the precast concrete wall panels, a major milestone in the construction process. After Thanksgiving, the structural steel contractors will be on-site to begin steel erection, marking another exciting phase in the project. Additionally, a sample of the concrete seating for the outdoor dining area was recently formed and approved.

In the next four weeks, the following tasks are planned:

  • Completion of sanitary and water utility installations
  • Finishing the precast concrete erection
  • Completing floor pour-backs
  • Beginning exterior wall framing
  • Starting structural steel erection

This progress is bringing us closer to achieving the vision of a state-of-the-art facility designed to serve the community with enhanced care and services. Thank you for your continued support as we build a brighter future for healthcare in Harrison County.