August Community Update

We are excited to share that the building footings, storm drainage, and underground utilities are underway. In addition, we successfully passed a surprise DNR inspection for the stormwater drainage.

4-Week Look-ahead:

  • Completion of the east parking lots
  • Finishing the building foundations
  • Installation of temporary power to the trailer and building pad
  • Underground building electrical and plumbing work
  • Curb & asphalt installation in the parking lots is expected within the next 4-6 weeks
  • Seeding around the public road, planning for mid-September when the weather cools
  • The remaining sidewalk work is also anticipated to be finished in mid-September

We are pleased to report that we remain scheduled for completion in April 2026.