April 2024 – Community Update

The weather has posed a challenge for the new hospital’s construction progress this month. As of today, there have been a total of 17 weather days. However, the project remains on schedule. The storm drains for the new 39th Street have been installed, and concrete curbs will be set up in the next few weeks. Currently, the relocation of the overhead power line and the 12″ water line is in progress. The next steps include the relocation of the 8″ water line and gas line. The grading around the pond is ongoing. The site is being monitored for compaction, and settlement plates have been installed.

Storm drain piping being backfilled with gravel 4/29/24.

Storm drain piping at inlet structure, 5/8/24

Site grading ongoing with large equipment

Secret Link

Epworth Sleepiness Scale

How likely are you to doze off or fall asleep in the following situations, in contrast to just feeling tired? This refers to your usual way of life in recent times. Even if you have not done some of these things recently, try to work out how they would have affected you.